Channel3000.comMadison News


E-Mail News Alerts
Get breaking news and daily headlines.
Browse all e-mail newsletters

DOT's 2008 Beltline Improvement Outline

Road Constructions For 2008, 2010-2012

Below is an outline of the scheduled projects that the Wisconsin Department of Transportation will undertake in conjunction with the Beltline improvement project:

Old Sauk 2008
  • Add Additional left turn lane on NB ramp
  • Add advance left turn lane for WB traffic between High Point and ramp terminal
  • SB exit ramp will have one left turn lane and two right turn lanes
  • Auxiliary lane extensions both north and south between the west ramp terminals and Excelsior Drive
  • NB exit ramp will have two left turn lanes and one right turn lane

Mineral Point 2008
  • Add triple left turn lanes to NB exit ramp
  • Extend NB exit ramp right turn lane
  • Add WB auxiliary lane between Target entrance and Beltline
  • Add SB exit ramp dual right turn lanes

Seminole Highway 2008
  • Provide signals and lane reconfiguration work at both ramp terminals and approaches
  • Bike pedestrian lane only provided on west side of bridge

Park Street 2008
  • Add additional left turn lane on the WB off ramp to provide one right turn

Park Street 2010/2012
  • Removal of existing EB on ramp and reconstruction with new alignment
  • Signalize NB movement at EB off ramp and Park Street
  • Removal of NB off ramp (loop ramp in SE quadrant of current configuration)
  • Relocation of frontage road to make room for SB and new NB exit ramp
  • Realign SB/NB exit ramp to straighten out
  • Create dual left turn lanes and connection from SB to NB terminal
  • Lengthen acceleration lane from EB on loop ramp through the bike and pedestrian bridge
  • Lengthen decal lane on Park Street to WE on ramp

Rimrock Road 2008
  • Add right turn lane on WB off ramp to provide for dual right turn lanes and one left turn lane

Between Rimrock and Park Street
  • Extension of auxiliary lanes on both side

U.S. Highway 51/Stoughton Road 2008
  • Add a third left turn lane on the EB off ramp
  • Add additional left and right turn lane on the WB off ramp

Fish Hatchery 2010/2012
  • Removal of remaining loop ramp from NB Fish Hatchery to WB Beltline traffic (NE quadrant of interchange)
  • Alignment of ramps on the north side of the interchange
  • Widen bridge to accommodate dual left turn lanes

Between Old Sauk and Gammon Roads 2008
  • Mill and pavement overlay both EB and WB lanes up to ramp terminals at each end



Links We Like

Sponsored Content
There is no absolute number of drinks per day that defines alcoholism. Learn the behavior and body reactions that constitute alcoholism. More Details

By designing a great outdoor living space you can quickly enhance the value of your home and make it more appealing to potential buyers. More Details

If you have aspirations of becoming a millionaire, check out these five habits that may be worth emulating. More Details

No matter where you live there are great foreclosed properties that could be just right for you. Search over 1.5 million foreclosed properties today and save up to 50% off market value! More Details